5–Validation Methods for DCB and FCoE
Validation Step 3—FCoE Function and I/O Tests
5-12 51031-00 A
Validation Step 3—FCoE Function and I/O Tests
Figure 5-12 shows the three test configurations that validate FCoE function and
I/O in the FCoE fabric:
Converged Network Adapter host > FCoE switch > FCoE storage
Converged Network Adapter host > FCoE switch > direct-attached Fibre
Channel storage
Converged Network Adapter host > FCoE switch > Fibre Channel switch >
Fibre Channel storage
Figure 5-12. I/O Test with Fibre Channel SAN Storage Setup
Validation Process
The following validation steps are used for all three test configurations:
1. Install the Medusa test tools (MLTT) on the Converged Network Adapter
host.
2. Map the target device from the MLTT client interface.
Converged Network Adapter Host > FCoE Switch > FCoE Storage
Converged Network Adapter Host > FCoE Switch > Direct Attached Fibre Channel Storage
Converged Network Adapter Host > Fibre Channel Switch > Fibre Channel Storage
4Gbps
10Gbps